Canoe Building Time-Line by John Lindman
Prepare Site - Day One
509-327-7902 voice and fax
barkcanoe@earthlink.net e-mail
Home
Canoes
Classes
Materials
Accessories
News and Stuff
Links
Consignment Canoes
Awning, fire pit, table, building bed, tank, heater
Prepare Root - Day One & Day Two
Insert in pot, bring to boil and let sit for 3 hours
Split
Remove bark
Prepare Thwarts - Day Three
Carve
Prepare Gunwales - Day Three
Bevel Inside Gunwale
Laminate Ends
Bend Ends
Prepare Stem Pieces - Day Three
Carve
Laminate
Bend
Prepare Sheathing - Day Four
Split blanks down for ribs and sheathing
Make sheathing blanks and then soak them
Pick out the various pieces and where they will go
Soak it
Prepare Ribs - Day Five
Split rib blanks
Carve ribs
Final prep of root and sheathing - Day Five
Final split and trim of sheathing pieces.
(Carve as necessary to get all pieces consistent in thickness)
Do final prep of sheathing - get each root consistent in size with all others
Roll-out Bark - Day Six
Weight it down
Cut gores
Bring up sides
Insert side panels
Stake into place
Check
Stitch - Day Seven & Eight
Mark line
Mark holes
Peg
Stitch
Insert Gunwales - Day Nine
Release inside stakes
Insert gunwales
Height Sticks
Clamp
Check
Lash Gunwales - Days Nine & Ten
Peg
Lash (to end thwart)
Insert Stems - Day Eleven
Peg one side
Trim bark
Peg other
Trim half way
Remove Frame
Insert Permanent Thwarts - Day Twelve
Make Mortise
Insert
Peg
Turn-up and Lash Gunwale Ends - Day Twelve
Make cardboard template
Trim bark
Lash
Do fancy lashing at end of gunwales or do bark deck
Bend Ribs - Day Thirteen
Bend
Install binder
Place in sun to dry
Pitch Inside - Day Fourteen
Prepare canvas
Mark all inside holes with felt pen
Pitch
Cover w/canvas
Insert Ribs and Sheathing - Day Fourteen
Insert Ashleaf or man-board - Day Fourteen
Carve
Fit
Apply Gunwale Cap - Day Fifteen
Make Pegs
Drill & Fit
Lash ends
Pitch outside - Day Fifteen
Prepare pitch
Pitch
Test - Day Fifteen
Place on saw horses
Add about an inch of water
Go underneath canoe and mark with pencil any leaks
(slosh water around to check all necessary areas)
Pitch as needed Maiden voyage!